David Edwards with students Drew Westen Emory College
About the Project
Psychology at Emory
Planning, Design & Construction
People
Giving Opportunities

For mor info contact joshua.newton@emory.edu

Planning, Design & Construction


Progress View

Aerial view of construction site

November 28, 2007

View previous pictures in the Photo Gallery.

Project Timeline

Design Schedule

  • Start - December 2005
  • Finish - September 2007

Construction Schedule

  • Start - October 2007
  • Finish - February 2009

Planning Meetings

Planning Group Samples Planning Discussion


Architectural Renderings

Schematic Designs
Floor Plans
Schematic Floor Plan

*Adobe Acrobat Reader is required to view PDF files.


Building Site Preparation


With the demolition of Gilbert and Thomson Halls (built in 1947) on Dickey Drive, construction for the new psychology building is set to begin in fall 2007.

The next step of the process calls for realigning North Oxford Road and Dickey Drive to create space for the building adjacent to Atwood Hall (chemistry).

Emory College

About the Project | Psychology at Emory | Planning, Design & Construction | People | Giving Opportunities
Emory College | Emory University

 

Copyright © Emory University
Last updated: December 14, 2007
Please direct questions or comments to college@emory.edu

Science Commons homepage Emory University